Bemina Bridge thrown open to public, restoration & repair completed

Budgam, Nov 15: Deputy Commissioner Budgam, Akshay Labroo today conducted an on-spot appraisal of the completed restoration work on the Bemina Bridge, a vital link between Budgam and Srinagar.

The DC reviewed retrofitting of the damaged expansion joints, an essential part of the project undertaken to enhance the bridge’s serviceability ensuring the safety and comfort of commuters.

The repair work was completed in a span of 14 days and was thrown open today after the completion of a minimum seven days period of setting of the restoration material.

On the occasion, the DC underscored the significance  of this vital bridge that connects two districts.

“The successful and timely completion of this project underscores the commitment of the administration for providing safe and smooth travel for all commuters and transporters using this Bridge,” the DC added.

The DC lauded the cooperation of the local people in extending support during the repair of this vital bridge.

Chief planning officer Budgam, officials of the R&B Division budgam, Tehsildar Budgam and other concerned officials were also present at the site.

Show More

Online Editor "Valley Vision"

Valley Vision News is your trusted source for authentic and unbiased news from the heart of Kashmir and beyond. We cover breaking news, culture, politics, and stories that matter, connecting local voices to global perspectives. Stay informed with us! "Empower your vision with truth, for every story has the power to change the world."

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button